PROGETTI

Progetto-11
ongoing

Extension works and functional adaptation of the purification plant of Sassoferrato.

CLIENT:

Multiservizi S.p.A. (Ancona)

TYPE OF TASK:

Construction management and security coordination during the execution step.

AMOUNT FOR THE PROJECT:

2.538.240,42 €

PERIOD OF TIME:

2017 - ongoing

Progetto-10
ongoing

Extraordinary maintenance services for the reconstruction of two distinguished factories located in the former military prison of Palermo.

CLIENT:

Interregional Public Works Office (Palermo)

TYPE OF TASK:

Security coordination during planning phase

AMOUNT FOR THE PROJECT:

3.942.056,00 €

PERIOD OF TIME:

2017 - ongoing

Progetto-9
ongoing

Characterization and management of wastewater (atmospheric, civil and industrial) produced within the plant in Via della Chimica – Feasibility analysis and definition of alternatives of treatment.

CLIENT:

SHIRE S.p.A. (Rieti)

TYPE OF TASK:

Preliminary, definitive and executive planning

AMOUNT FOR THE PROJECT:

Currently under development

PERIOD OF TIME:

2017 - ongoing

Progetto-8
ongoing

Pumping stations and ground sewer main collectors at service of the purification plant of Recco.

CLIENT:

IRETI S.p.A. - Mediterranea delle Acque S.p.A. (Genova)

TYPE OF TASK:

Preliminary, definitive and executive planning

AMOUNT FOR THE PROJECT:

Currently under development

PERIOD OF TIME:

2016 – ongoing

Progetto-7
completed

Hygienic-sanitary restoration of the community of Torriglia (outer portion of the city)

CLIENT:

IREN AG - Mediterranea delle Acque S.p.A. (Genova)

TYPE OF TASK:

Preliminary, definitive and executive planning

AMOUNT FOR THE PROJECT:

4.127.139,25 €

PERIOD OF TIME:

2014

Progetto-6
completed

Installation of backwash water treatment plant for the purification plant in the South of Rome. Biofiltration phase “back-wash” wastewater treatment plant – Roma Sud Wastewater Treatment Plant (WWTP)

CLIENT:

Acea Elabori S.p.A. (Roma)

TYPE OF TASK:

Ongoing testing and static testing in c.a

AMOUNT FOR THE PROJECT:

6990.000,00 €

PERIOD OF TIME:

2012 - 2017

Progetto-5
completed

Construction of new technological volumes and volumes of service for the wastewater purification plant in the communities of: Recco – Avegno – Uscio – Camogli – Pieve Ligure. Placement of walking routes and routes for vehicles.

CLIENT:

Mediterranea delle Acque S.p.A. (Genova)

TYPE OF TASK:

Coordination of security at design phase

AMOUNT FOR THE PROJECT:

600.000,00 €

PERIOD OF TIME:

2015 - 2016

Progetto-4
completed

Adjustment and strengthening of the wastewater purification plant for the communities of Recco, Avegno, Uscio, Camogli, Sory and Pieve Ligure.

CLIENT:

IREN AG - Mediterranea delle Acque S.p.A. (Genova)

TYPE OF TASK:

Construction management and support to the supervisor of the procedure

AMOUNT FOR THE PROJECT:

18.559.574.19 €

PERIOD OF TIME:

2014 - 2016

Progetto-3
completed

Adjustment and strengthening of the purification plant of Melegnano until 30,000 A.E. - First phase.

CLIENT:

CAP Holding S.p.A. (Milano)

TYPE OF TASK:

Functional and technical-administrative trial in progress and during the final phase.

AMOUNT FOR THE PROJECT:

2.583.799,28 €

PERIOD OF TIME:

2015 - 2016

Progetto-2
completed

Census and characterization of small dykes (H ≤ 15 M E V ≤ 1 MMC) located in the National Park of Sila: preparation of a GIS platform to collect and systematically store data.

CLIENT:

Parco nazionale della Sila

TYPE OF TASK:

Major activities and preparation of a web-based GIS platform

AMOUNT FOR THE PROJECT:

--

PERIOD OF TIME:

2013

Progetto-1
completed

Waste removal and restoration of the property of the military range of Capo Frasca – Arbus (VS).

CLIENT:

NSPA - NATO Support and Procurement Agency

TYPE OF TASK:

Coordination of security at design phase

AMOUNT FOR THE PROJECT:

862.000,00 €

PERIOD OF TIME:

2015